Risk identification and allocation of the utility tunnel PPP project
Abstract
Based on the literature study of utility tunnel, 60 project risk factors are identified through expert interviews and classified into macro level risks, meso level risks and micro level risks according to the risk level. At the same time, we study the risk-sharing mechanism, then adopt the control force principle, the cognition principle and the profit principle to allocate risk, and put forward the pertinent risk countermeasure in order to provide the reference for the future practice and theory research.
- Publication:
-
Materials Science, Energy Technology, and Power Engineering i: 1st International Conference on Materials Science, Energy Technology, Power Engineering (MEP 2017)
- Pub Date:
- May 2017
- DOI:
- 10.1063/1.4982497