J-PARC Neutrino Beamline Upgrade Technical Design Report
Abstract
In this document, technical details of the upgrade plan of the J-PARC neutrino beamline for the extension of the T2K experiment are described. T2K has proposed to accumulate data corresponding to $2\times{}10^{22}$ protons-on-target in the next decade, aiming at an initial observation of CP violation with $3\sigma$ or higher significance in the case of maximal CP violation. Methods to increase the neutrino beam intensity, which are necessary to achieve the proposed data increase, are described.
- Publication:
-
arXiv e-prints
- Pub Date:
- August 2019
- DOI:
- 10.48550/arXiv.1908.05141
- arXiv:
- arXiv:1908.05141
- Bibcode:
- 2019arXiv190805141A
- Keywords:
-
- Physics - Instrumentation and Detectors;
- High Energy Physics - Experiment